Preptics
Tutorial

Changing your test date

How to move the date, and what happens to work you have already done.

Test dates move. The plan is built to survive it.

  1. Open your plan.
  2. Edit the survey and pick the new date from the calendar.
  3. Save. The schedule rebuilds immediately.

What is keptLink to the section: What is kept

Everything you have completed stays completed. Lessons you have finished are not reset, your proficiency is untouched, and your mock results are unaffected. What changes is the ordering and the daily load between now and the new date.

What the verdict may doLink to the section: What the verdict may do

Moving a date closer can flip the realism verdict from comfortable to tight or ambitious. That is the plan telling you the arithmetic changed, not the plan being pessimistic — it shows what the verdict was calculated from so you can judge it yourself.

Did this answer your question?

If not, ask — answered questions are added to this help centre.